Development Roadmap

Our Plan

Four phases. A funded starting point. Honest milestones. We'll tell you what we planned, what happened, and what comes next.

Phase by Phase

The Development Plan

Q3 2026

Phase 1 — Land & Prep

Finalize land position and surface access agreements

Complete well location surveys and regulatory filings

Mobilize drilling contractor and supply chain

Finalize participation documentation with investors

Q4 2026

Phase 2 — Initial Drill

Drill and case first well(s)

Run production logging and evaluate results

Begin facility tie-in and surface reclamation

Report results to all participants

H1 2027

Phase 3 — Evaluate & Expand

Analyze production data against pre-drill model

Make go/no-go decision on follow-up locations

Drill additional wells if Phase 2 results support it

Optimize production and operating costs

2027+

Phase 4 — Sustained Development

Systematic development of remaining locations

Ongoing production optimization

Evaluate strategic options as asset matures

Maintain transparent reporting to all participants

On capital and expectations

Our initial program is fully funded. We are not raising capital to survive — we are offering participation to people who want to be part of what we're building.

We will share detailed financial projections, well economics, and capital allocation with anyone who has introduced themselves and is seriously evaluating participation. We don't publish those numbers publicly — not because we're hiding anything, but because context matters and we'd rather have that conversation directly.

If Phase 1 results support expansion, we will communicate that clearly and offer existing participants first right of participation in subsequent phases.